Progress of the work on the Light Train in Mexico

COMSA Corporación continues to make progress in the specialised maintenance work on the section of the Mexican Light Train between Azteca Stadium and Xochimilco. The works are at 85% completion and the section is expected to be operational by the end of this year.

On  October 31, the Director General of Electric Transport of Mexico City, Guillermo Calderón, and the Secretary of Mobility, Andrés Lajous, visited the location together with the Director of the Mexican delegation of COMSA, Jordi Frigola, where they were able to see the track rehabilitation work being carried out.

The project includes the complete replacement of the tracks, the renovation of the platform and drainage, and the complete rehabilitation of the 8 vehicle crossings, among other maintenance tasks. Once the work is completed, travel time between the Azteca Stadium and Xochimilco will be reduced by 40% and the service offered will reach 130,000 users per day.