Project for the expansion of the railway network between Malmö and Lund, from 2 to 4 tracks. Among the most important issues that motivate their construction is the excessive noise that occurs with current lines and the intersection with the E6 motorway connecting with the rest of Europe. In addition, 5 km of temporary roads will be built to keep excess line traffic during construction works. The planning stage is expected to continue until 2016, while contacts with suppliers will be held until 2017, the same year in which construction will begin and completed in 2022. Although the project is divided into several sections, there will only be one tender for the contract of the entire project (design and construction).

Budget: SEK 3,800 million